Works on site update

Works are now well underway on site with the access spur and crane pads completed – see attached photos -and the turbine foundations are due to be completed in early October. Turbines will then arrive later in October once foundations have

Shares still available

We are still counting up the last late applications – there have been many! It appears that we are still short of the target by around £350,000. We’re working to put bridging finance in place so we can continue towards installation as soon as

Share extension announced

Heartland Community Wind is over a third of the way to the target with nearly £700,000 raised to date but we’ve still got plenty of shares available. We’re therefore extending the share offer until 10 July 2015. We’ve had a